Building Permit Details
Permit Number: 25-06676
Permit Status: Completed
Permit Type: Building
Project Type: Commercial
Description of Work: CM - Commercial
Scope of Work: New
Issued Date: 12/18/2025
CO Issue Date: 08/07/2026
Plans Examiner: Stuart Foster
Job Address: 7979 BUTTE CREEK ST LITTLETON, CO 80125
Building Code: 2021 IBC
Scheduled Inspections
Name Date Scheduled Estimated Time of Inspection
Engineering Letters
Engineering Letters will be listed below if they are required for your project. They must be submitted before scheduling above ground inspections.
Required Engineering Letters Received Date
Caisson/Footer/WG Letter 01/15/2026
Steel Letter 01/15/2026
Survey 04/20/2026
Inspection History
Name Date Occurred Result Inspector Name Inspection Comments Meter Release Inspection Report
Ceiling Closure HVAC Partial 04/01/2026 Cancelled Anthony Frank Incorrect inspection scheduled.  
Drywall Partial 04/14/2026 Disapproved Anthony Frank The restrooms are required to have from the wet wall, left side and right side 5 foot den shield in lieu of half-inch type X sheet rock.
Rooms 103, 104, 105, 106, 107, 108, 110, 111, 112, 113, 114, 115 and 160 are OK to proceed. Please check screw patterns per plan detail as requested.. please show corrections on the next inspection.
 
Drywall Partial 05/14/2026 Approved Anthony Frank This will be for the second floor walls only.  
Drywall Partial 05/19/2026 Approved Anthony Frank Southwest side area walls/reception area drywall partial is completed.  
Exterior Lath Partial 04/14/2026 Approved Anthony Frank The south west side exterior partial inspection is approved, OK to proceed  
Exterior Lath Partial 05/19/2026 Approved Anthony Frank The level EFIS there’s approved, may proceed.  
Exterior Wall Sheathing 03/04/2026 Disapproved Duke Thompson West wall exterior coating already applied. No way to verify screw patterns. Interior 8” wall incomplete.  
Exterior Wall Sheathing Partial 01/27/2026 Approved Anthony Frank Sheet S201 and S505, The yellow highlighter marked for exterior wall sheet panels.
Please provide copies all engineering letters to the county, uploading all MEP documentation would be appreciated
 
Exterior Wall Sheathing Partial 02/27/2026 Disapproved Dusty Welz 1. East elevation of main building is P1 shear wall. Complete 4/12 fastener patterns. Many sheets not completed or spacing exceeds tolerances. Spacing between fastened supports shall not exceed 16”.
2. West elevation Is P2 shear walls. Complete 3/12 fastener spacing. Many sheets not completed or spacing exceeds tolerances. Spacing between fastened supports shall not exceed 16”. Please provide detailed RFI for replacing the CS16 with flat steel to include fastener spacing details at shear wall openings.
 
Exterior Wall Sheathing Partial 03/23/2026 Disapproved Robert Stratton 1. West classroom wall approved from the north corner to the south corner all floors.
2. Robert will make a drawing of the buildings perimeter and all sheating inspections should be documented with the walls numbered for inspection so we can document each numbered wall approval or disapproval.
3. Inspectors please be as descriptive as possible.
 
Exterior Wall Sheathing Partial 03/31/2026 Approved Dusty Welz 1. Approved for North facing elevations except lower-north kitchen wall, east elevation of gym and south elevation of gym to grid line 13.
2. Missing seam blocking on north kitchen elevation and opening strapping.
3. See blue highlighter on separated sheet S2.01.
 
Exterior Wall Sheathing Partial 04/01/2026 Approved Anthony Frank See Sheet S2.01, notes four,five,three, two at 14.
See the blue highlighter
 
Exterior Wall Sheathing Partial 04/06/2026 Approved Anthony Frank This will complete the exterior wall SHEATHING, any liquid applied weather resistant barrier is all third-party letters required to be submitted to DC E plans, provide permit number and address. Notify the front desk at this data is being sent in.  
Final Building 07/28/2026 Disapproved Anthony Frank 1. Submit all third-party letters, upload to E plans. provide all necessary, inspection, sign, offs, i.e. health department, fire department, electrical department, plumbing department.
2. Install paddle handles and all gang bathrooms, thumb twist are not acceptable.
3. Per sheet A1.02 the right side swing is incorrect for the E grass exit gate, plans reference two leafs. The directional swing is incorrect.
4.Per sheet A1.02, Keynote number eight the safe dispersal area signage is incorrect, reverse north and south. SIGNAGE.
5. USE THE CORRECT AGENCY FOR ALL ELEVATOR INSPECTIONS.
 
Final Building 07/30/2026 Disapproved Anthony Frank Previous correction, items are incomplete, correct as required and recall for inspection.  
Final Building 08/05/2026 Disapproved Anthony Frank Building correction items have been completed to satisfactory, final building approval is pending for final elevator inspection.  
Final Building 08/07/2026 Approved Matt Dziubanski All items have been corrected.

Ok to issue CO
 
Final Electric 08/06/2026 Approved Tim Pendleton Inspection completed by State of Colorado  
Final Energy Compliance 07/24/2026 Disapproved Anthony Frank General courtesy walk for completion.  
Final Energy Compliance 08/05/2026 Approved Anthony Frank  
Final HVAC 07/28/2026 Disapproved Anthony Frank Provide an upload testing balance report for the HVAC system/submit commissioning report to E plant.  
Final HVAC 08/05/2026 Approved Anthony Frank The final tab report for the HVAC system has been reviewed and approved. Thank you.  
Final Plumbing 08/06/2026 Approved Tim Pendleton Inspection completed by the State of Colorado (DORA)  
Floor Truss 02/09/2026 Disapproved Anthony Frank Preference sheet A3.11, reflective, ceiling plan, or highlighter, this is a partial inspection.  
Floor Truss 04/08/2026 Disapproved Anthony Frank 1.R116 ,R102 missing clips north and south, C16 strapping on plate breaks.
2. Missing H25, A35, both sides.
3. Rooms 202,204,206 missing lateral blocking.
4. B1d floor trusses appear to be in the wrong location, should it be on top of a shear wall.
 
Foundation Insulation 01/02/2026 Approved Duke Thompson Foundation insulation, partially backfilled around entire foundation, third-party letters needed by final  
Insulation Thermal Partial 04/13/2026 Approved Dusty Welz First floor classrooms exterior wall vapor barrier/ insulation thermal inspection. See pink highlighter on A0.11. Seal all penetrations and rips in vapor barrier and Complete all top plate straps at steel column intersections.  
Insulation Thermal Partial 04/22/2026 Approved Anthony Frank  
Insulation Thermal Partial 05/08/2026 Approved Anthony Frank This will be a partial first floor Southwest entry and reception area/lobby area, insulation and vapor barrier. To include ceilings.
This will be a partial Northwest Stairway insulation inspection, and vapor barrier to include ceilings
 
Insulation Thermal Partial 05/14/2026 Approved Anthony Frank For the south wall in the gymnasium, OK to proceed.  
Insulation Thermal Partial 05/19/2026 Approved Anthony Frank The insulation inspection or the gymnasium is completed.  
Moisture Barrier Partial 04/07/2026 Disapproved Anthony Frank All CMU walls liquid applied adhesive are healings will require a third-party inspection.  
Moisture Barrier Partial 04/08/2026 Disapproved Anthony Frank Provide ESR reports on how to attach the EFIS , provide adhesive and nailing attachment.
Resolve the flashing issue that was previously discussed.
 
Roof Truss 04/16/2026 Disapproved Richard Miller Not ready  
Roof Truss 04/16/2026 Cancelled Richard Miller Duplicate  
Roof Truss 04/22/2026 Approved Anthony Frank All blocking and all share walls and embracing is completed, receive the engineers report proved to good to go  
Roof Truss Partial 04/08/2026 Disapproved Anthony Frank 1.Provide RFI for repairs on vertical webbing stair well 1 roof trusses. Engineered repair letter.
2. Reference sheet S5.05 detail 10 and sheet S5.20 detail attachments.
3. Reference MYTECH INSTRUCTIONS and bracing is missing throughout.
4. SW foyer trusses are not completed.
5. Corridors ledger attachments details are lacking.
 
Rough Frame 04/22/2026 Disapproved Anthony Frank Room 218 and the stairwell are missing the tempered glass windows come these items are backordered. OK to proceed and install a recall for inspection.  
Rough Frame 04/23/2026 Disapproved Dusty Welz Kitchen:
1. Anchor bolts are incomplete on exterior wall at plumbing stacks.
2. Strap top plates at steel post by service window.
3. Complete trimmer brackets on interior door jamb.
Electrical room:
1. Fix top plates at steel strap right side of door. Red arrow.
2. Minimum 2 anchor bolts per bottom plate.
Gym:
1. Anchor bolt with in 12” of bottom plate end by north exterior door. Also missing with in 12” at every column.
2. Exterior corners need to be fastened 24” OC up corner studs.
Please schedule partial inspections until all areas have been approved:
Front entry needs cleared out for inspection.
Under stairs still incomplete.
Shafts are incomplete.
 
Rough Frame 06/25/2026 Approved Anthony Frank Final grid seal to cover on the second floor is completed with the exception of room 206. OK to proceed with ceiling recall 206 when completed and fire separation wall has been done.  
Rough Frame Partial 01/28/2026 Approved Anthony Frank Sheet A2.11, reference the green highlighter for exterior and interior walls, this is partial  
Rough Frame Partial 04/01/2026 Approved Anthony Frank Sheet S2.01 the corridor pressure blocking.  
Rough Frame Partial 04/06/2026 Disapproved Anthony Frank The second Floor was not ready for inspection.
Please provide contact information in the work task at hand previously, but you pay attention to what inspections you are scheduling
 
Rough Frame Partial 04/06/2026 Approved Anthony Frank Reference Sheet S2.01 the orange highlighter. Rooms this will be the first floor framing, interior frame for exterior wall walls.
Rooms 103, 104, 105, 106, 112, 113, 114, 115, 116, 117, 902, 904, and 903.

Schedule the Correct inspections with a sheet number and a description of what is to be expected that day with contact information
This item is been discussed previously numerous times
 
Rough Frame Partial 04/08/2026 Disapproved Anthony Frank Not ready  
Rough Frame Partial 04/10/2026 Approved Duke Thompson 1. Second floor, interior shear walls screw pattern, complete at upper portion
2. Tighten screws installed bottom plate, main floor, corridor room 1 02, 114, 115, 116
 
Rough Frame Partial 04/14/2026 Disapproved Anthony Frank The corridor to include rooms 202, 203, 204, 205, 206, 207, 209, 214, 215, 216, 217, 218, 219. OK.
All holddowns must be completed as with fire, stopping for all MEP penetrations. Not OK.
Stairwell number one is required to have tempered glass right hand side not OK
Room 218 door swing must have tempered glass., Within 24 inches. Not OK.
Please correct as required and recall for inspection.
 
Rough Frame Partial 04/16/2026 Disapproved Richard Miller Not ready  
Rough Frame Partial 04/17/2026 Disapproved Anthony Frank 1. Room 216 is lacking a post, correct as required and recall for inspection.
2.Room 218 is lacking strapping to be completed.
3. Room 215 is locking the holddowns as requested, please walk all units to make sure we are code compliant, this came up the last two visits.
4. Room 214 is lacking beam and strapping.
5., PEASE provide information with the draft stopping material used.

PLEASE LEAVE THESE AREAS, UNCOVERED TO BE REINSPECTED, OK TO PROCEED AT THE BUILDERS OWN RISK.
 
Rough Frame Partial 04/27/2026 Approved Anthony Frank Sheet A2.11 reference the orange highlighter. Hard lids completed restrooms and storage areas. Chef wall observed by stairwell one first floor incomplete.
Correction items in the gymnasium. Several anchor bolts were not completed, currently Tim is working on this to completed the by end of business day 04/27/26. OK to proceed.
 
Rough Frame Partial 05/01/2026 Disapproved Anthony Frank The southwest front corner right angle high wall stud is not attached properly, a role blocking is not installed on the horizontal attachments
Correct as required and recall for rough frame inspection when completed.
 
Rough Frame Partial 05/05/2026 Approved Anthony Frank Corrections at Southwest entry were completed, grease trap not stalled at this point.  
Rough Frame Partial 05/19/2026 Approved Anthony Frank The two stairwells are completed for rough frame, as well as the restroom ceilings are completed.
The reception area Southwest side overhead area is completed.
The tempered glazing has been completed on the stairwells in the second floor window close to the door swing.
 
Rough Frame Partial 05/22/2026 Approved Anthony Frank  
Rough Frame Partial 07/09/2026 Approved Duke Thompson  
Rough HVAC Partial 04/02/2026 Approved Dusty Welz Supply and return Hard duct on first floor for classrooms, bathrooms, corridor, conference room and back of house rooms as highlighted green on M1.01A. HVAC Insulation and ceiling closure inspections required when ready.  
Rough HVAC Partial 04/22/2026 Approved Anthony Frank ALL HVAC penetrations from the first floor to the second floor are completed.  
Rough HVAC Partial 05/14/2026 Approved Anthony Frank This will be for the second floor above ceiling, HVAC inspection, joints and seams. OK to proceed.  
Rough HVAC Partial 06/01/2026 Approved Anthony Frank 1. This will be inclusive of rough HVAC/insulation for first floor classrooms.
Not completed is the kindergarten room number 116 and the corridor hallway.
2. This will be for the second floor HVAC /insulation shafts. Not to include room 202 is not completed. OK to proceed.
 
Rough HVAC Partial 06/08/2026 Approved Anthony Frank Rooms 202, 206, 208, 209, 216 and 218.  
Rough Plumbing Partial 04/06/2026 Disapproved Anthony Frank All plumbing inspections I believe our schedule with the state, DORA. Please pay attention to what inspections are being called out.
Provide page numbers and work task with contact information
 
Shaft Wall Partial 04/22/2026 Approved Anthony Frank The SHAFT wall separating the HVAC exhaust and supply lines is approved that backs up to the stairwell.  
Shaft Wall Partial 05/01/2026 Approved Anthony Frank Touching up the shaft wall with FS1. To be completed by end of business day 05/01/26 per Tim.
 
Structural Floor Partial 02/09/2026 Approved Anthony Frank Sheet A311 reference the reflective ceiling plan, the orange highlighter.