Building Permit Details
Permit Number: 24-01909
Permit Status: Issued
Permit Type: Building
Project Type: Residential
Description of Work: RS - Custom
Scope of Work: New
Issued Date: 05/24/2024
CO Issue Date:
Plans Examiner: Stuart Foster
Job Address: 9900 SARA GULCH CIR PARKER, CO 80138
Building Code: 2021 IRC
Scheduled Inspections
Name Date Scheduled Estimated Time of Inspection
Engineering Letters
Engineering Letters will be listed below if they are required for your project. They must be submitted before scheduling above ground inspections.
Required Engineering Letters Received Date
Caisson/Footer/WG Letter 08/07/2024
Steel Letter 08/07/2024
Survey 10/24/2024
Inspection History
Name Date Occurred Result Inspector Name Inspection Comments Meter Release Inspection Report
Caisson Deck/Pole Barn 06/25/2024 Disapproved Fredrick Mooney 1. Unable to verify cage for piers. Form pour complete. Supply engineer letter for 2 piers.
2. North side of property appears to have a retaining wall. Supply engineering for retaining wall and revise plans to show location etc.
 
Drywall 11/05/2024 Approved Brian Schroder  
Electric Service Equipment 01/31/2025 Approved Curt Elliott Pool house panel  
Electric Trench 07/16/2024 Approved Justin Lett Note-1-1/2” PVC north side of house to SE corner of pool house  
Exterior Lath 09/04/2024 Disapproved Rick Chadwick Caulk around all penetrations  
Exterior Lath 09/05/2024 Approved Rick Chadwick  
Exterior Wall Sheathing 08/01/2024 Disapproved Rick Chadwick See plans for shear nailing at corners and check for 6” perimeter nailing throughout  
Exterior Wall Sheathing 08/08/2024 Approved Rick Chadwick  
Final Building 01/31/2025 Disapproved Fredrick Mooney Need retaining wall to be closed before final for pool house can be approved.  
Final Building 02/12/2025 Approved Clayton Rodeback  
Final Electric 01/31/2025 Approved Curt Elliott Service corrections to be addressed on a separate permit.  
Final Plumbing 01/31/2025 Approved Fredrick Mooney  
Foundation Insulation 06/25/2024 Approved Fredrick Mooney  
Insulation Thermal 10/30/2024 Approved Richard Miller  
Interior Gas Line 10/25/2024 Disapproved Fredrick Mooney Need 10 psi test. Rough ok. Insulate at your own risk. Ok to insulate per electrical inspector.  
Interior Gas Line 10/30/2024 Approved Richard Miller  
Midroof 08/12/2024 Disapproved Rick Chadwick Not ready minimum 30% of tiles installed, all batts, and all paper  
Midroof 08/14/2024 Approved Rick Chadwick  
Preliminary Defensible Space 02/12/2024 Approved Jill Welle
Roof Truss 08/01/2024 Disapproved Rick Chadwick Provide engineering plans  
Roof Truss 10/25/2024 Approved Fredrick Mooney  
Rough Electric 10/25/2024 Disapproved Justin Lett Ok to insulate pending frame approval. Recall when outdoor bar is wired.

Note-UFER in east wall of bar area. Must remain accessible

**Service upgrade for house requires separate permit. Currently (2)-150s and panel changed to (2)-200s. Provide voltage drop calc and all provisions of 225.41 will be required at house due to distribution equipment change. DC amendment requires voltage drop on dwelling feeders be 3% or less**
 
Rough Electric 10/30/2024 Disapproved Justin Lett 10/25 corrections incomplete  
Rough Frame 10/25/2024 Disapproved Fredrick Mooney 1. Np plumbing pipes in bathroom top plates.
2. Stud shoe ext wall x 6 at wet bar.
3. Therma guard at back of fireplace.
4. Draftstop fireplace stud bays or cap top chase to attic.
5. Attic vent required 1/300 sq ft.
Ok to insulate per electrical inspector.

Recall with insulation.
 
Rough Frame 10/30/2024 Approved Richard Miller  
Ufer Ground Electrode 06/25/2024 Disapproved Justin Lett Foundation already poured-provide engineer letter  
Underground Plumbing 07/16/2024 Disapproved Fredrick Mooney Need 5 psi test. Pipe not supported at 45 degrees offset at exterior wall/corner.  
Underground Plumbing 07/18/2024 Approved Brian Schroder Adjust kitchen sink drain to achieve 1/8” minimum slope. Correct as required.