Building Permit Details
Permit Number: 22-00473
Permit Status: Completed
Permit Type: Building
Project Type: Residential
Description of Work: RS - Custom
Scope of Work: New
Issued Date: 03/10/2022
CO Issue Date: 11/04/2022
Plans Examiner: Stuart Foster
Job Address: 8449 LOST LAKE DR FRANKTOWN, CO 80116
Building Code: 2018 IRC
Scheduled Inspections
Name Date Scheduled Estimated Time of Inspection
Engineering Letters
Engineering Letters will be listed below if they are required for your project. They must be submitted before scheduling above ground inspections.
Required Engineering Letters Received Date
Caisson/Footer/WG Letter 03/29/2022
Steel Letter 03/29/2022
Survey 04/07/2022
Inspection History
Name Date Occurred Result Inspector Name Inspection Comments Meter Release Inspection Report
Caisson Deck/Pole Barn 09/19/2022 Approved Rick Chadwick  
Construction Meter 05/06/2022 Approved Justin Lett CORE 05/06/2022
Drip Edge 08/11/2022 Approved Rick Chadwick  
Driveway Form 11/02/2022 Cancelled June Amicucci Not a form inspection layer road base
Driveway Preliminary 01/28/2022 Approved June Amicucci
Drywall 08/26/2022 Approved Rick Chadwick  
Electric Service Equipment 05/05/2022 Disapproved Justin Lett 1. Need construction meter fee paid 2. Float neutrals at temp 3. Need feeder EGC in conduit to temp sized to upstream OCPD 4. Approved meter blank 5. Bushing at connectors per 300.4 6. Protect #8 or use larger GEC  
Electric Service Equipment 05/06/2022 Cancelled Justin Lett Duplicate-Construction meter inspection is scheduled  
Electric Service Equipment 10/27/2022 Disapproved Justin Lett 1. Emergency disc sign missing per 230.85 at disc on house 2. 14AWG not permitted on 20A breaker in exterior panel 3. Secure HRs above panel within 12” 4. Missing screws at both panels.

Note-UFER in Basement directly behind exterior disc
 
Electric Service Equipment 10/31/2022 Approved Justin Lett CORE 10/31/2022
Electric Trench 04/07/2022 Disapproved Justin Lett Trench required to be 24” to top of conductors entire length  
Electric Trench 04/08/2022 Approved Justin Lett Note-250urd w/#2 EGC ped to basement wall  
Exterior Lath 10/26/2022 Approved Rick Chadwick  
Exterior Wall Sheathing 06/27/2022 Approved Rick Chadwick  
Final Building 11/02/2022 Disapproved Rick Chadwick 1. Post permanent address on structure 4” high, 1/2” stroke, contrasting color 2. Install downspouts and extensions 3. Splash blocks at sill cocks 4. Caulk all penetrations at siding 5. Handrail to turn in top and bottom 6. Maximum riser height 7 3/4” and cannot vary more than 3/8” on flight of stairs 7. Lateral tie backs at deck 8. Maximum riser height at garage stairs to top of threshold 7 3/4” 9. Grippable handrail at RV garage 10. Adjust self closing door at garage 11. Tempered glazing required at bathroom off hall to garage  
Final Building 11/04/2022 Approved Rick Chadwick  
Final Defensible Space 11/02/2022 Cancelled Steve Dwyer Inspection not required
Final Driveway 11/03/2022 Approved June Amicucci Should have more road base but will pass.
Final Electric 10/27/2022 Disapproved Justin Lett 1. Service not approved 2. A/C service GFCI inoperable 3. Closet, hall receps require GFCI protection within 6’ of sinks 4. Add recep outside of cab right of FP to cover wall space 5. Need additional recep on island 6. Cover horizontal cables in garage wall 7. Missing GFCI protected at RV garage 8. Blank plate missing at RV garage ceiling 9. Need permit for basement finish-currently has some walls framed and wired—install plates at boxes with devices and blank off all other boxes. Cover horizontal cables on both sides of unfinished walls 10. Bond screw in well disc loose  
Final Electric 10/31/2022 Approved Justin Lett Separate permit required for basement prior to any further work being performed. Some walls already framed and rough wiring installed.  
Final Energy Compliance 11/02/2022 Disapproved Rick Chadwick Provide ladder for attic access  
Final Energy Compliance 11/04/2022 Approved Rick Chadwick  
Final HVAC 11/02/2022 Approved Rick Chadwick See Final Building  
Final Plumbing 11/02/2022 Approved Rick Chadwick See Final Building  
Fireblocking 08/11/2022 Approved Rick Chadwick  
Foundation Insulation 03/29/2022 Approved Clayton Rodeback  
Insulation Thermal 08/15/2022 Disapproved Rick Chadwick Not ready  
Insulation Thermal 08/16/2022 Approved Rick Chadwick  
Interior Gas Line 08/08/2022 Cancelled Gary Hartmann see Rough Frame  
Interior Gas Line 08/10/2022 Approved Rick Chadwick Black Hills Energy 08/10/2022
Midroof 08/02/2022 Approved Rick Chadwick N/A on composite roofs  
Moisture Barrier 08/02/2022 Cancelled Rick Chadwick Cancell call Weather Resistant Barrier and repair items as discussed  
Preliminary Defensible Space 01/20/2022 Approved Jill Welle
Roof Truss 06/27/2022 Disapproved Rick Chadwick Provide truss layout plan no inspection  
Roof Truss 08/02/2022 Disapproved Rick Chadwick Provide truss layout plan and drawings NO INSPECTION  
Roof Truss 08/09/2022 Approved Rick Chadwick  
Rough Electric 08/03/2022 Cancelled Thomas Buzo Building not dried in. Roof missing. Install tyvek or garage doors.  
Rough Electric 08/08/2022 Disapproved Justin Lett 1. High recep in RV garage cannot be on bay circuit 2. Lower level exterior lights and receps incomplete 3. Staple in laundry and basement ceiling 4. Runners at NM within 6’ of access

Note-floor heat requires inspection and cannot be located in closets
 
Rough Electric 08/09/2022 Disapproved Justin Lett Corrections from previous inspection incomplete-please note that upper hall smoke alarm is required to be at least 3’ horizontally from bathroom door that contains shower or tub-missed getting this on last inspection report  
Rough Electric 08/11/2022 Approved Justin Lett  
Rough Energy Compliance 08/10/2022 Disapproved Rick Chadwick 1. Complete air barriers and outlet receptacles  
Rough Energy Compliance 08/11/2022 Approved Rick Chadwick  
Rough Frame 08/08/2022 Cancelled Gary Hartmann Roof Truss inspection must pass before calling Rough Frame inspection  
Rough Frame 08/10/2022 Disapproved Rick Chadwick 1. Complete post at stair cantilever to pad  
Rough Frame 08/11/2022 Approved Rick Chadwick  
Shower Pan 09/19/2022 Disapproved Rick Chadwick Not ready  
Shower Pan 10/06/2022 Approved Nick Martinell  
Slab Electrical 09/20/2022 Approved Thomas Buzo Heat sensors not installed at time of inspection. Note: sensor wire shall maintain 1” clearance from heat cables.

In-floor heat at laundry, bath by garage, master bath and JJ bath.
 
Ufer Ground Electrode 03/30/2022 Approved Wayne Elmore Engineer Letter  
Underground Plumbing 03/29/2022 Approved Clayton Rodeback  
Weather Resistive Barrier 08/10/2022 Approved Rick Chadwick Should be Weather Resistive Barrier