Building Permit Details
Permit Number:
24-12238
Permit Status:
Completed
Permit Type:
Building
Project Type:
Residential
Description of Work:
RS - Basement
Scope of Work:
Alteration
Issued Date:
08/05/2024
CO Issue Date:
Plans Examiner:
Christopher Polanski
Job Address:
10122 ATLANTA ST PARKER, CO 80134
Building Code:
2021 IRC
Inspections
Contractors
Permit Fees
Property Details
Structure Details
Documents
JavaScript and Session Cookies must be enabled for this Site.
Scheduled Inspections
Name
Date Scheduled
Estimated Time of Inspection
Engineering Letters
Engineering Letters will be listed below if they are required for your project. They must be submitted before scheduling above ground inspections.
Required Engineering Letters
Received Date
Inspection History
Name
Date Occurred
Result
Inspector Name
Inspection Comments
Meter Release
Inspection Report
Drywall
09/10/2024
Approved
Duke Thompson
Maintain inch and a half float gap at bottom of drywall
Print Report
Final Building
10/11/2024
Approved
Richard Miller
Complete combustion transfer grills as required
Print Report
Final Electric
10/11/2024
Disapproved
Henry VanSchaack
1) Ssbj from main neutral bar to supplemental neutral bar on enclosure must be sized per 250.104 (#4 copper or equivalent)
2) grommet required at dishwasher cord passing through cabinet per 422.16
Print Report
Final Electric
10/15/2024
Approved
Justin Lett
Print Report
Interior Gas Line
09/03/2024
Cancelled
Fredrick Mooney
N/A
Print Report
Rough Electric
09/03/2024
Disapproved
Justin Lett
1. 300.4-recep in flat stud wall bottom of stairs, soffits 2. NPs at top plates where drywall was cut to fish down dry walled walls, above sub panel 3. Recep below 5’6” required in mech room 4. Flat NM cables not permitted to be stapled on edge 5. Secure sub feed SER at 4-1/2’ intervals 6. Listed add-a-lugs required for subfeed neutral and EGC in main panel 7. Bond hard gas piping with #6 CU or equivalent upstream of yellow CSST fitting
Print Report
Rough Electric
09/04/2024
Approved
Henry VanSchaack
** Ssbj from main neutral bar to supplemental neutral bar on enclosure must be sized per 250.104 (#4 copper or equivalent), correct and proceed, will check at final **
Print Report
Rough Frame
09/03/2024
Approved
Fredrick Mooney
Print Report
Shower Pan
09/16/2024
Disapproved
Duke Thompson
1. Leak at liner pan, retest
2. Install pre-slope underneath liner pan
Print Report
Shower Pan
09/17/2024
Disapproved
Richard Miller
Shower pan leaking. Need retest and reinspection
Print Report
Shower Pan
09/18/2024
Approved
Richard Miller
Print Report
Underground Plumbing
08/27/2024
Approved
Richard Miller
Rough plumbing ok
Print Report