Building Permit Details
Permit Number: 23-21414
Permit Status: Completed
Permit Type: Building
Project Type: Commercial
Description of Work: CM - Commercial
Scope of Work: New
Issued Date: 06/26/2024
CO Issue Date: 07/21/2025
Plans Examiner: Stuart Foster, Wayne Elmore
Job Address: 8367 N RAMPART RANGE RD LITTLETON, CO 80125
Building Code: 2021 IBC
Scheduled Inspections
Name Date Scheduled Estimated Time of Inspection
Engineering Letters
Engineering Letters will be listed below if they are required for your project. They must be submitted before scheduling above ground inspections.
Required Engineering Letters Received Date
Caisson/Footer/WG Letter 02/20/2025
Steel Letter 02/20/2025
Survey 02/20/2025
Inspection History
Name Date Occurred Result Inspector Name Inspection Comments Meter Release Inspection Report
Construction Meter 09/24/2024 Disapproved Henry VanSchaack 1) provide fault current calculations to verify type of cold sequence fuses required
2) bond supply side metal raceway per 250.92
3) bottom GFCI recep must be wr type per 406.9
 
Construction Meter 09/25/2024 Approved Henry VanSchaack Xcel 09/25/2024
Drip Edge 03/24/2025 Approved Fredrick Mooney  
Drywall 03/24/2025 Disapproved Fredrick Mooney Partial approved. Complete bathroom, foyer and mechanical.  
Drywall 03/26/2025 Approved Robert Stratton All drywall completed and approved.  
Electric Service Equipment 04/02/2025 Disapproved Jonathan Pastore 1. 250.24(4) MBJ wire type sized per 250.102C1 If the main bonding jumper specified in 250.28 is a wire or busbar and is installed from the grounded conductor terminal bar or bus to the equipment grounding terminal bar or bus in the service equipment, the grounding electrode conductor shall be permitted to be connected to the equipment grounding terminal, bar, or bus to which the main bonding jumper is connected.
200.2(B) Continuity. The continuity of a grounded conductor shall not depend on a connection to a metal enclosure, raceway, or cable armor.
2. CT cabinet bonding jumper shall be sized per 250.102C1
3. Engineer letter states exothermic welding connections to ground rods
 
Electric Service Equipment 04/03/2025 Approved Jonathan Pastore Will verify Cadweld connections to two 3/4”x8’ ground rods @ final Xcel 04/04/2025
Electric Trench 03/06/2025 Cancelled Jonathan Pastore Changing to trench partial  
Electric Trench 03/07/2025 Approved Jonathan Pastore Pile base detail #6 CU tails for lot lights  
Electric Trench Partial 10/31/2024 Approved Matt Mazzara Consultation to discuss site lighting  
Electric Trench Partial 03/06/2025 Approved Jonathan Pastore Laterals: 2x4” with 4” spare (schedule 80 @ expansion coming from grade)
2 Sump lines 2x3/4” each
Site lighting 3/4” new (existing pole lights 1”). Monument sign coming out of ground box separate inspection) **missing bonding for pole base detail**
 
Exterior Lath 04/22/2025 Approved Brian Schroder  
Exterior Wall Sheathing 01/28/2025 Approved Robert Stratton  
Final Building 05/13/2025 Approved Robert Stratton  
Final Electric 05/12/2025 Disapproved Jeremy Bock 1. GFCI protection required at door opener outlets
2. GFCI protection required at receptacle within 6 ft of sink basin at utility room
3. Below grade outlets require GFCI protection-check all
4. GFCI receptacle at tanks in basement must be readily accessible
5. Cover photo eye to test monument sign
Note-fire dept and final building inspections not approved
 
Final Electric 05/13/2025 Disapproved Jonathan Pastore 1. Heater ceiling receptacles shall be GFCI protected  
Final Electric 05/14/2025 Approved Jonathan Pastore  
Final HVAC 05/07/2025 Disapproved Robert Stratton 1. Reschedule final HVAC inspection with final building inspection, after fire department final inspection approval is completed.
2. Provide TAB report.
 
Final HVAC 05/08/2025 Cancelled Robert Stratton Reschedule final HVAC with final building inspection after fire department final inspection is approved and a final electric inspection has been performed.  
Final HVAC 05/13/2025 Approved Robert Stratton  
Final Plumbing 05/07/2025 Approved Robert Stratton  
Insulation Thermal 03/13/2025 Approved Duke Thompson Drying all penetrations at roofline  
Insulation Thermal Partial 01/28/2025 Cancelled Robert Stratton Voids above overhead Garage doors verified.  
Interior Gas Line 02/19/2025 Approved Robert Stratton 20lbs test Xcel 02/19/2025
Interior Gas Line 02/19/2025 Cancelled Richard Miller All roughs are to be scheduled together, ie rough frame and energy compliance  
Moisture Barrier 04/22/2025 Approved Brian Schroder  
Roof Truss 01/28/2025 Approved Robert Stratton  
Rough Electric 02/28/2025 Approved Henry VanSchaack  
Rough Electric 04/11/2025 Approved Jonathan Pastore Ground rods per engineered plan with exothermic welds  
Rough Electric Partial 09/23/2024 Cancelled Henry VanSchaack GC Cancelled  
Rough Electric Partial 09/23/2024 Cancelled UnassignedBldg Cancelled by Web user.  
Rough Frame 03/13/2025 Approved Duke Thompson Fire block, mechanical chase at top in mechanical room  
Rough HVAC 03/12/2025 Approved Duke Thompson Need duct at FAU  
Rough HVAC Partial 02/28/2025 Approved Duke Thompson Ductwork only above customer service room  
Rough Plumbing Partial 02/19/2025 Approved Robert Stratton Basement rough plumbing inspected today and plumbing test verified good.  
Ufer Ground Electrode 11/13/2024 Approved Jonathan Pastore One line drawing shows #4 connected to re-bar by Caldwell, omitted. Provide letter from engineer for acceptance since it isn’t following the stamped drawing.

1/0 copper for UFER matches one-line