Building Permit Details
Permit Number: 21-07504
Permit Status: Completed
Permit Type: Building
Project Type: Commercial
Description of Work: CM - Tenant Finish
Scope of Work: New
Issued Date: 08/27/2021
CO Issue Date: 12/16/2021
Plans Examiner: Anthony Petty
Job Address: 7120 E COUNTY LINE RD Unit #203 1, HIGHLANDS RANCH, CO 80126
Building Code: 2018 IBC
Scheduled Inspections
Name Date Scheduled Estimated Time of Inspection
Engineering Letters
Engineering Letters will be listed below if they are required for your project. They must be submitted before scheduling above ground inspections.
Required Engineering Letters Received Date
Inspection History
Name Date Occurred Result Inspector Name Inspection Comments Meter Release Inspection Report
Ceiling Closure HVAC 11/15/2021 Disapproved Gary Hartmann Plenum wrap not installed per mfg. requirements  
Ceiling Closure HVAC 11/17/2021 Approved Gary Hartmann  
Ceiling Rough Electric 11/11/2021 Cancelled UnassignedBldg Cancelled by Web user.  
Ceiling Rough Electric 11/17/2021 Approved Henry VanSchaack  
Control Lighting 12/09/2021 Approved Henry VanSchaack  
Drywall 10/25/2021 Approved Clayton Rodeback  
Final Building 12/15/2021 Approved Gary Hartmann  
Final Electric 11/11/2021 Cancelled UnassignedBldg Cancelled by Web user.  
Final Electric 12/09/2021 Approved Henry VanSchaack Pending fire department approval  
Final HVAC 11/15/2021 Disapproved Gary Hartmann Not ready, ceiling closure not approved
All tiles need to be dropped for final HVAC inspection
Provide balance report for final HVAC
 
Final HVAC 11/23/2021 Approved Gary Hartmann  
Final Plumbing 11/15/2021 Disapproved Gary Hartmann Complete plenum wrap  
Final Plumbing 11/17/2021 Approved Gary Hartmann  
Firestopping 12/15/2021 Cancelled Gary Hartmann N/A  
Rough Electric 10/20/2021 Approved Henry VanSchaack Walls  
Rough Frame 10/20/2021 Approved Gary Hartmann Rough framing complete  
Rough Frame Partial 10/20/2021 Approved Gary Hartmann  
Rough HVAC 10/20/2021 Approved Gary Hartmann  
Rough Plumbing 10/20/2021 Approved Gary Hartmann PVC in plenum needs to be wrapped in plenum wrap