Scheduled Inspections
Name Date Scheduled Estimated Time of Inspection
Engineering Letters
Engineering Letters will be listed below if they are required for your project. They must be submitted before scheduling above ground inspections.
Required Engineering Letters Received Date
Inspection History
Name Date Occurred Result Inspector Name Inspection Comments Meter Release Inspection Report
Drywall 12/20/2019 Approved Kerry Keller  
Final Building 02/25/2020 Cancelled Kerry Keller Cancelled by contractor to office  
Final Building 03/25/2020 Approved Kerry Keller  
Final Electric 02/25/2020 Disapproved Rick Sugar See scanned ticket  
Final Electric 03/04/2020 Cancelled Rick Sugar Cx by Contractor  
Final Electric 03/26/2020 Disapproved Rick Sugar ARC fault the outlets in the sitting room area( ok to use a arc fault receptacle)
ARC fault the wet bar lighting and outlets
ARC fault circuit #5
 
Final Electric 03/26/2020 Cancelled Rick Sugar Could not be at the house to do a virtual inspection  
Final Electric 03/31/2020 Cancelled Rick Sugar Cancelled by the contractor at 11:11 am  
Final Electric 04/07/2020 Approved Damon Montroy This inspection was done as a virtual inspection due to COVID19  
Interior Gas Line 12/13/2019 Approved Kerry Keller  
Rough Electric 12/13/2019 Disapproved Rick Sugar Per Douglas county amendments 10 openings on a 15 amp circuit
NEED to list a electrical contractor
Outlet required left of the fireplace and allow 11/4" NM to face of the stud
Box fill exceeded right of the wet bar sink
Ok to sheet rock
Check HR terminations
ARC fault throughout , except North exterior wall
 
Rough Electric 12/20/2019 Approved Henry VanSchaack Liste electrical contractor on permit prior to final, hr’s will be checked at final  
Rough Frame 12/13/2019 Approved Kerry Keller